Case study
University of Wisconsin Music Performance Building
Details
This unique structure had several custom architectural and application requirements, supported by a hybrid mix of steel, concrete walls, and glulam beams. We used Tekla Structures to provide precise structural steel details and created accurate panel books for the concrete and rebar. The completed building featured a 650-seat main concert hall, a 320-seat recital hall, an orchestral rehearsal room, and more.
Project highlights include variable acoustics, integrated recording, high-end finishes, unique architectural precast. This project will serve as a “gateway” to the UW Madison campus, as it is the first official campus building along University Ave, a main arterial road throughout downtown Madison.
The structure of the building is a hybrid of steel, concrete walls, and a few glulam beams. Steel framing and decking rises from the basement and supports all floors and roof areas. However, the Concert Hall is framed by 80’ tall walls poured with self-consolidating concrete and braces steel on all sides. Large concrete acoustical chambers also rise 30’+ from a supported concrete slab on the second-floor level. The roof of the Recital Hall is framed by glulam beams and wooden decking. The exterior will consist of curtainwall window systems, V-Shaped precast panels, metal panels, and stone veneer.
EOR: R.A. Smith National
AOR: Holzman Moss Bottino Architecture
GC: J. P. Cullen and Sons, Inc.
Design: Strang Inc.
Winner of the 2018 North America BIM Awards in the multi-material category.
Location
Madison, WI
Materials
600 Tons of Steel
5700 Cubic Yards of Concrete
300 Tons of Rebar
Size
75,000 square feet